The project is located near the north city of Hefei,and uses an ammonia and carbon dioxide cascade system,21 ice wheel open screw compressors,and matching bucket pump units.It is green,environmentally friendly,and energy-saving.This project is a renovation project,which is difficult to construct while reconstructing;
Yili plant adopts 5S management,and all our construction operations must comply with Yili's management requirements.The company has invested more than 90 construction management personnel,which took more than 7 months from mobilization to the end of construction.It has overcome various difficulties,worked overtime to debug,and ensured that the equipment was started up and put into production on time.This has played a key role in Yili's order delivery,winning high recognition from production management personnel.